What happens when you prepare my building licence documents for lodgement?
Once your construction drawings have been amended to include any pre start variations and are 100% completed we will obtain structural drawings from the engineer which takes approximately 4 weeks. Once this is received, your plans and Engineering are required to go through a certification stage before lodgement. This process takes approximately 2 weeks. Once we have all the relevant paperwork signed and approved we are ready for lodgement! Once in council the average turnaround time is 10 days.